Letting results · Alabama Department of Transportation
April 24, 2026 letting results
Fast-published project results from the freshest available state snapshot.
18trusted project results recorded on this date.
| Project | Description | Bidders | Bidder amounts and ranks | Low bid | Total bids | First–second gap |
|---|---|---|---|---|---|---|
| ATRP2-07-2022-007 | INTERSECTION IMPROVEMENTS (GRADING, DRAINAGE, AND PAVEMENT) TO INCLUDE TURN LANE AND ACCELERATION LANE | 3 | #1 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.2M; #2 APAC-ALABAMA, INC.: $1.2M; #3 MCELHENNEY CONSTRUCTION CO., LLC: $1.7M | $1.2M | $4.1M | $25,230 |
| BR-0053(608) | FOR CONSTRUCTING THE BRIDGE DECK REHABILITATION (HYDROBLASTING) AND TRAFFIC STRIPE ON SR-53 (US-231) OVER THE | 4 | #1 F&W CONSTRUCTION COMPANY, INC.: $1.7M; #2 American Contracting & Services, Inc.: $2.1M; #3 Gibson & Associates, Inc.: $2.2M; #4 COMANCHE CONSTRUCTION OF GEORGIA, LLC: $2.3M | $1.7M | $8.3M | $374,424 |
| IM-I065(550), IM-I065(551) | REST AREA NORTHBOUND I-65 NEAR GREENVILLE (SITE CONSTRUCTION) ON I-65 NEAR GREENVILLE | 5 | #1 S. A. GRAHAM COMPANY, INC.: $11.7M; #2 TRIPTEK CONSTRUCTION, LLC: $11.8M; #3 SITE PROS, LLC: $12.5M; #4 W. S. NEWELL & SONS, INC.: $13.1M; #5 TAYLOR & MIREE CONSTRUCTION, INC: $14.8M | $11.7M | $63.9M | $42,404 |
| NH-0005(577) | RESURFACING AND TRAFFIC STRIPE ON SR-5 FROM THE JUNCTION OF CHURCH STREET TO THE JUNCTION OF SANDPIT ROAD IN | 3 | #1 ASPHALT CONTRACTORS, INC.: $1.2M; #2 APAC-ALABAMA, INC.: $1.4M; #3 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.6M | $1.2M | $4.2M | $201,147 |
| NH-FMGR-0067(516) | MICRO-MILLING, RESURFACING, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-67 FROM THE JUNCTION OF THE SR-24 | 3 | #1 ROGERS GROUP, INC.: $1.0M; #2 GRAYSON CARTER & SON CONTRACTING, INC.: $1.2M; #3 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.5M | $1.0M | $3.7M | $170,510 |
| NH-FMGR-HSIP-0079(527) | SAFETY WIDENING, MICRO-MILLING, RESURFACING (SCRUB SEAL), GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-79 | 3 | #1 DUNN CONSTRUCTION COMPANY, INC.: $2.4M; #2 APAC-ALABAMA, INC.: $2.6M; #3 WIREGRASS CONSTRUCTION COMPANY, INC.: $3.2M | $2.4M | $8.1M | $118,917 |
| STPAA-0116(501) | THIN LIFT OVERLAY, SCRUB SEAL, AND TRAFFIC STRIPE ON SR-116 FROM THE JUNCTION OF SR-17 TO THE JUNCTION OF SR-39 IN | 1 | #1 S. T. BUNN CONSTRUCTION COMPANY, INC.: $2.3M | $2.3M | $2.3M | Not available |
| STPAA-0216(508) | STRUCTURAL REMOVAL ON SR-216 AT THE I-20/I-59 INTERCHANGE (EXIT 100) EAST OF LAKEVIEW | 2 | #1 IKAROS, LLC: $191,500; #2 MCELHENNEY CONSTRUCTION CO., LLC: $219,575 | $191,500 | $411,075 | $28,075 |
| STPAA-0283(502) | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-283 FROM THE JUNCTION OF SR-25 (US-411) TO THE JUNCTION OF | 3 | #1 WIREGRASS CONSTRUCTION COMPANY, INC.: $725,567; #2 VULCAN MATERIALS ASPHALT AND CONSTRUCTION,: $905,623; #3 ALABAMA GRADING & EXCAVATION, LLC.: $951,109 | $725,567 | $2.6M | $180,056 |
| STPAA-FMGR-0025(573) | RESURFACING (SCRUB SEAL), GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-25 (US-411) FROM THE JUNCTION OF | 5 | #1 WIREGRASS CONSTRUCTION COMPANY, INC.: $2.6M; #2 APAC-ALABAMA, INC.: $3.1M; #3 VULCAN MATERIALS ASPHALT AND CONSTRUCTION,: $3.1M; #4 ALABAMA GRADING & EXCAVATION, LLC.: $3.3M; #5 DUNN CONSTRUCTION COMPANY, INC.: $3.5M | $2.6M | $15.7M | $470,987 |
| STPAA-HSIP-0016(540) | STRIPE ON SR-16 (US-90) FROM THE JUNCTION OF THE I-10/SR-16 (US-90) EASTBOUND ROUNDWAY RAMP TO THE INTERSECTION | 2 | #1 APAC-ALABAMA, INC.: $1.4M; #2 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.4M | $1.4M | $2.8M | $2,716 |
| STPAA-HSIP-0025(572) | SAFETY WIDENING, MICRO-MILLING, RESURFACING (SCRUB SEAL), AND TRAFFIC STRIPE ON SR-25 (US-231) FROM THE JUNCTION | 4 | #1 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.8M; #2 VULCAN MATERIALS ASPHALT AND CONSTRUCTION,: $2.0M; #3 ALABAMA GRADING & EXCAVATION, LLC.: $2.2M; #4 DUNN CONSTRUCTION COMPANY, INC.: $2.4M | $1.8M | $8.4M | $260,759 |
| STPAA-HSIP-0069(580) | SAFETY WIDENING, MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-69 FROM A POINT NEAR JACKSON CREEK (MP | 2 | #1 WIREGRASS CONSTRUCTION COMPANY, INC.: $2.6M; #2 APAC-ALABAMA, INC.: $3.1M | $2.6M | $5.7M | $494,199 |
| STPAA-HSIP-0171(520) | MICRO-MILLING, RESURFACE (SCRUB SEAL), TRAFFIC SIGNAL UPGRADES (BACKPLATE REPLACEMENTS AND SIGNAL | 2 | #1 S. T. BUNN CONSTRUCTION COMPANY, INC.: $2.5M; #2 ROGERS GROUP, INC.: $2.7M | $2.5M | $5.1M | $191,955 |
| STPBH-3719(251) | MICRO-MILLING, RESURFACING, AMERICAN WITH DISABILITIES ACT (ADA) UPGRADES, TRAFFIC SIGNS, AND TRAFFIC STRIPE ON | 3 | #1 APAC-ALABAMA, INC.: $4.1M; #2 DUNN CONSTRUCTION COMPANY, INC.: $4.2M; #3 WIREGRASS CONSTRUCTION COMPANY, INC.: $5.1M | $4.1M | $13.4M | $66,913 |
| STPMB-MR25(911) | TRAFFIC SIGNAL UPGRADES AT SIGNALIZED INTERSECTIONS ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN THE SOUTHWEST | 3 | #1 BAGBY & RUSSELL ELECTRIC COMPANY, INC.: $100,000; #2 BIG RIVER ELECTRIC, INC.: $127,459; #3 TEMPLE J ELECTRIC, LLC: $154,925 | $100,000 | $382,384 | $27,459 |
| STPMN-2626(250) | PLANING, RESURFACING, AND TRAFFIC STRIPING ON CR-259 (HOGAN RD) FROM CR-143 TO SR-111 (SITE 1) AND CR-228 | 3 | #1 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.1M; #2 ASPHALT CONTRACTORS, INC.: $1.2M; #3 APAC-ALABAMA, INC.: $1.3M | $1.1M | $3.5M | $64,967 |
| STPSU-5225(250) | ROADWAY IMPROVEMENTS (RECONSTRUCTION) ON CHURCH STREET FROM THE JUNCTION OF SR-3 (US-31/6TH AVENUE) TO THE | 3 | #1 ROGERS GROUP, INC.: $669,215; #2 GRAYSON CARTER & SON CONTRACTING, INC.: $829,782; #3 WIREGRASS CONSTRUCTION COMPANY, INC.: $1.1M | $669,215 | $2.6M | $160,567 |
Back to the state market · How results are calculated
Last updated September 16, 2026 with source data through August 28, 2026. See the methodology and data dictionary or report a correction.