Letting results · Alabama Department of Transportation

July 26, 2024 letting results

Fast-published project results from the freshest available state snapshot.

9trusted project results recorded on this date.
Apparent low bids and reported bidder counts.
ProjectDescriptionBiddersBidder amounts and ranksLow bidTotal bidsFirst–second gap
AL-20240726029MAINTENANCE BRIDGE PAINTING ON SR-21 OVER THE SCENIC TRAIL SOUTHWEST OF BEATRICE AND OVER FLAT CREEK4#1 SOUTHERN COATINGS OF TARPON SPRINGS, LLC: $281,635; #2 Elite Industrial Painting, Inc.: $347,600; #3 M & J CONSTRUCTION COMPANY OF PINELLAS: $445,235; #4 Southern Road & Bridge, LLC: $503,746$281,635$1.6M$65,965
ATRP2-63-2022-123ACCESS MANAGEMENT IMPROVEMENTS ON SR-216 FROM THE JUNCTION OF COVERED BRIDGE ROAD TO THE JUNCTION OF5#1 BULLS CONSTRUCTION GROUP, LLC: $1.5M; #2 CB&A CONSTRUCTION, LLC.: $1.5M; #3 MCELHENNEY CONSTRUCTION CO., LLC: $1.5M; #4 Cornerstone Civil Contractors, LLC: $1.6M; #5 GILLESPIE CONSTRUCTION, LLC: $1.8M$1.5M$7.9M$22,725
BR-0022(537)BRIDGE PAINTING AND BRIDGE REHABILITATION ON SR-22 OVER THE COOSA RIVER NORTHEAST OF VERBENA3#1 Cekra, Inc.: $3.3M; #2 Gibson & Associates, Inc.: $4.1M; #3 Southern Road & Bridge, LLC: $5.6M$3.3M$13.0M$799,405
CMAQ-7030(600)ROADWAY IMPROVEMENTS AND SIDEWALK INSTALLATION ON CR-42 (MASSEY ROAD) FROM THE JUNCTION OF SR-3 (US-31) TO4#1 CB&A CONSTRUCTION, LLC.: $4.6M; #2 BULLS CONSTRUCTION GROUP, LLC: $5.1M; #3 GILLESPIE CONSTRUCTION, LLC: $5.9M; #4 RUSSO CORPORATION: $7.1M$4.6M$22.7M$476,294
IM-I059(440)TRAFFIC SIGN REHABILITATION ON I-20/I-59 FROM THE SUMTER COUNTY LINE TO THE JEFFERSON COUNTY LINE AND ON I-359 TO2#1 Superior Traffic Control, LLC: $994,952; #2 OZARK SAFETY SERVICES, LLC: $1.1M$994,952$2.1M$87,640
LRSI-3624(250)ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL INSTALLATIONS) ON CR-48 OVER STRINGER CREEK IN SECTION (SITE 1) AND ON2#1 ALABAMA GUARDRAIL, INC.: $218,490; #2 C & H Construction Services, LLC: $232,539$218,490$451,029$14,049
RACRNH-RACRIM-I059(429)RECONSTRUCTION & LANE ADDITION (GRADE, DRAIN, PAVE, BRIDGE) ON I-59 FROM I-459 TO CR-10 (CHALKVILLE MOUNTAIN3#1 WIREGRASS CONSTRUCTION COMPANY, INC.: $70.4M; #2 DUNN CONSTRUCTION COMPANY, INC.: $72.9M; #3 APAC-ALABAMA, INC.: $74.0M$70.4M$217.2M$2.5M
STPMN-2624(251)RESURFACING AND TRAFFIC STRIPE ON CR-66 FROM CR-209 TO THE SR-170 (SITE 1) AND ON CR-192 FROM SR-170 EAST TO3#1 ASPHALT CONTRACTORS, INC.: $596,186; #2 APAC-ALABAMA, INC.: $648,747; #3 WIREGRASS CONSTRUCTION COMPANY, INC.: $674,452$596,186$1.9M$52,561
STPSU-CRPAU-4123(253)RESURFACE, SIDEWALK INSTALL, TRAFFIC SIGNAL UPGRADES, STRIPE ON PEPPERELL PARKWAY FROM THE JUNCTION OF4#1 D & J ENTERPRISES, INC.: $2.5M; #2 BULLS CONSTRUCTION GROUP, LLC: $2.6M; #3 MCELHENNEY CONSTRUCTION CO., LLC: $3.0M; #4 GILLESPIE CONSTRUCTION, LLC: $3.2M$2.5M$11.3M$34,229